Space Rocket History #155 – Apollo 7 – Assembly, Testing, Training, and Launch

Command Service Module-101 started through the manufacturing cycle early in 1966. By July, it had been formed, wired, fitted with subsystems, and made ready for testing. After the Apollo 1 fire in January 1967, changes had to be made, mainly in the wiring, hatch areas, and the forward egress tunnel. It was December before the spacecraft came back into testing. CSM-101 passed through a three-phase customer acceptance review; during the third session, held in Downey on May 7th 1968, no items showed up that might be a “constraint to launch.” North American cleared up what few deficiencies there were (13) and shipped the craft to Kennedy on  May 30th 1967…