Space Rocket History #149 – Apollo 5: Lunar Module’s First Flight

“The fire-in-the-hole abort was the most critical test of the mission and one we had to accomplish successfully prior to a manned mission.” Gene Kranz – Flight Director Apollo 5

Apollo 5 Mission Patch

Apollo 5 Mission Patch

Lunar Module 1 delivered to the Cape

Lunar Module 1 delivered to the Cape

LM 1 mated to the spacecraft lunar module adapter

LM 1 mated to the spacecraft lunar module adapter

LM 1 inside adapter being hoisted to the booster

LM 1 inside adapter being hoisted to the booster

Apollo 5 on the launch pad

Apollo 5 on the launch pad

Apollo 5 lift off

Apollo 5 lift off

Jul 23

Space Rocket History #122 – Apollo: Serious Problems with the Lunar Module and Grumman

Toward the end of January 1967, it was revealed that Lunar Module 1 would not reach the Cape in February, as expected. This meant, the moon landing might be delayed because the lander was not ready. But the mission planners could not wait for the Apollo engineers to iron out all the problems. They had to plan for a landing in 1969 and hope that the hardware would catch up with them.

Lunar Module Diagram

Lunar Module Diagram

John Disher Explains the Components of the Apollo Program

John Disher Explains Apollo Components

Lunar Module Test Article LTA-2R

Lunar Module Test Article LTA-2R