After the uncertain days of February 1967, NASA officials began to realize that a recovery from the tragedy was under way. Through hard work and problem solving, morale of Nasa personnel started to improve…
Toward the end of January 1967, it was revealed that Lunar Module 1 would not reach the Cape in February, as expected. This meant, the moon landing might be delayed because the lander was not ready. But the mission planners could not wait for the Apollo engineers to iron out all the problems. They had to plan for a landing in 1969 and hope that the hardware would catch up with them.
At various stages of lunar module design, mockup reviews were conducted to demonstrate progress and identify weaknesses. These inspections were formal occasions, with a board composed of NASA and contractor officials and presided over by a chairman from the Apollo office in Houston.
The Lunar Lander originally had two docking hatches, one at the top center of the cabin and another in the forward position, or nose, of the vehicle, with a tunnel in each location to permit astronauts to crawl from one pressurized vehicle to the other…